2-3-21-snyatie-i-ustanovka-fazovrashhatelya.html
2.3.21. Removal and installation of the phase shifterRemoval
Remove the pump of high pressure.
Unscrew bolts.
Remove the vacuum pump.
|
Fig. 2.158. Fastening of the case of the regulator of phases of gas distribution
|
Remove the case of the regulator of phases of gas distribution (fig. 2.158).
Combine a mark in a cam-shaft gear wheel with a mark in the protection cover of a gear belt. Dredging stands vertically the friend opposite to the friend (fig. 2.153).
Turn off the fixing screw of the phase shifter a face nozzle.
Squeeze a natyazhitel of a chain And yes put him on a clamp In (fig. 2.160).
|
Fig. 2.160. Installation of a natyazhitel on a clamp
|
Unscrew the fixing screw of the phase shifter and remove it together with a chain.
Installation
Cam-shafts should be stopped a clamp of cam-shafts (fig. 2.159).
Put on a chain the phase shifter.
Put the phase shifter before a final cam-shaft to combine a cut And with a thorn In (fig. 2.161).
|
Fig. 2.161. Combination of the phase shifter and final cam-shaft
|
In such situation lay a chain at first from above on an asterisk of an inlet cam-shaft (fig. 2.162).
Slowly scroll an inlet cam-shaft a key on two openings in the direction of an arrow A until the phase shifter sits down on a cam-shaft (fig. 2.163).
|
Fig. 2.163. Installation of the phase shifter on a cam-shaft
|
NOTE
If the pin on enters a cut, it is necessary to remove and to anew establish a chain.
|
Tighten a bolt of fastening of the phase shifter. For this purpose use a face nozzle.
Further installation and assembly is carried out in the return to sequence removal.
Establish an inlet collector.
Establish TNVD.
Install the vacuum pump.
|